- DL/T5210.6-2009电力建设施工质量验收及评价规程第6部分:水处理剂制氢设备和系统(英文版)
- 电力企业联合会
- 799字
- 2025-02-15 05:33:17
4.10 Hydrogen Station
4.10.1 Installation of modular hydrogen generation device.
1 Scope of application:modular hydrogen generation device.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.1.
Table 4.10.1 Installation of modular hydrogen generation device

Table 4.10.1(Continued)

4.10.2 Installation of electrolytic bath.
1 Scope of application:hydrogen generation electrolytic bath.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.2.
Table 4.10.2 Installation of electrolytic bath

Table 4.10.2(Continued)

4.10.3 Installation of supporting frame.
1 Scope of application:installation of electrolytic bath supporting frame.
2 Inspection quantity:check them piece by piece.
3 Quality standards and inspection methods are as shown in Table 4.10.3.
Table 4.10.3 Installation of supporting frame

4.10.4 Installation of hydrogen-oxygen separator and scrubber.
1 Scope of application:hydrogen,oxygen separator and scrubber.
2 Inspection quantity:check them one by one.
3 Quality standards and inspection methods are as shown in Table 4.10.4.
Table 4.10.4 Installation of hydrogen-oxygen separator and scrubber

4.10.5 Installation of hydrogen-oxygen pressure regulator.
1 Scope of application:hydrogen,oxygen pressure regulator.
2 Inspection quantity:check them one by one.
3 Quality standards and inspection methods are as shown in Table 4.10.5.
Table 4.10.5 Installation of hydrogen-oxygen pressure regulator

Table 4.10.5(Continued)

4.10.6 Installation of driers.
1 Scope of application:installation of molecular sieve type dryer.
2 Inspection quantity:check them one by one.
3 Quality standards and inspection methods are as shown in Table 4.10.6.
Table 4.10.6 Installation of driers

4.10.7 Installation of hydrogen storage tanks.
1 Scope of application:hydrogen station.
2 Inspection quantity:check them one by one.
3 Quality standards and inspection methods are as shown in Table 4.10.7.
Table 4.10.7 Installation of hydrogen storage tanks

Table 4.10.7(Continued)

4.10.8 Installation of coolers.
1 Scope of application:hydrogen station.
2 Inspection quantity:check them one by one.
3 Quality standards and inspection methods are as shown in Table 4.10.8.
Table 4.10.8 Installation of coolers

4.10.9 Installation of alkali liquor storage tank.
1 Scope of application:hydrogen station.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.9.
Table 4.10.9 Installation of alkali liquor storage tank

4.10.10 Installation of water seal.
1 Scope of application:hydrogen station.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.10.
Table 4.10.10 Installation of water seal

4.10.11 Installation of fire protector.
1 Scope of application:hydrogen station.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.11.
Table 4.10.11 Installation of fire protector

4.10.12 Installation of manifolds.
1 Scope of application:hydrogen station,oxygen adding device.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.12.
Table 4.10.12 Installation of manifolds

4.10.13 Installation of hydrogen bottles,CO2 bottles.
1 Scope of application:hydrogen station.
2 Inspection quantity:check them item by item.
3 Quality standards and inspection methods are as shown in Table 4.10.13.
Table 4.10.13 Installation of hydrogen bottles,CO2 bottles

4.10.14 Installation of hydrogen,oxygen pipes.
1 Scope of application:hydrogen,oxygen system.
2 Check quantity:check them section by section according to the system.
3 Quality standards and inspection methods are as shown in Table 4.10.14.
Table 4.10.14 Installation of hydrogen,oxygen pipes

4.10.15 Installation of hydrogen station valves.
1 Scope of application:hydrogen generation system.
2 Inspection quantity:check them one by one.
3 Quality standards and inspection methods are as shown in Table 4.10.15.
Table 4.10.15 Installation of hydrogen station valves

4.10.16 Adjustment of hydrogen station valves.
1 Scope of application:hydrogen,oxygen system,feedwater oxygen adding devices.
2 Inspection quantity:all valves of the hydrogen station.
3 Quality standards and inspection methods are as shown in Table 4.10.16.
Table 4.10.16 Adjustment of hydrogen station valves

4.10.17 Tightness test of hydrogen station.
1 Scope of application:hydrogen,oxygen system,feedwater oxygen adding device.
2 Inspection quantity:all the equipment and pipes participating in the test.
3 Quality standards and inspection methods are as shown in Table 4.10.17.
Table 4.10.17 Tightness test of hydrogen station

Table 4.10.17(Continued)

4.10.18 Inspection of the compulsory provision implementation of the hydrogen station shall conform to Table 4.10.18.
Table 4.10.18 Inspection table of compulsory provision implementation of the hydrogen station

Table 4.10.18(Continued)
